ARTICLE · CHANGE MANAGEMENT

Standard, normal and emergency changes explained

Learn how standard, normal and emergency changes differ, which approval each one needs and how to keep urgent changes under control.

A colleague needs a new virtual machine from the standard template. A team wants to upgrade the database behind the invoicing system. And at 2 a.m., a security alert shows that a server must be patched immediately.

All three are changes, but you would not want to handle them in the same way. The first is routine and the second needs careful review. The third cannot wait. That is why change management distinguishes three types of change.

Why do changes have different types?

If every change gets the same heavy approval, routine work slows to a crawl and people look for shortcuts. If every change gets a light approval, risky work slips through. Types let you match the level of control to the level of risk.

What is a standard change?

A standard change is a low-risk, well-understood change that is done often and follows a documented procedure. ITIL 4 describes it as pre-authorised: the approval is given once, for the procedure, and not again for every individual change.

Typical examples:

  • Installing a standard piece of software from an approved list
  • Creating a user account in a defined way
  • Replacing a failed component with an identical one
  • Applying a routine, tested patch in a documented way

What makes a change standard is not that it is small. It is that it is repeatable, predictable and proven. A standard change needs a clear procedure, a known risk and a backout route, all agreed in advance.

What is a normal change?

A normal change is anything that is not standard and not an emergency. It is planned, assessed and authorised before it is carried out. Examples are a major application upgrade, a change in network architecture or the introduction of a new service component.

The approval depends on the risk. A low-risk normal change can be approved by one person who knows the service. A high-risk change may need several approvers, or a discussion in a change advisory board. Decide in advance who may approve what.

What is an emergency change?

An emergency change must be carried out as soon as possible, because waiting would cause serious harm: a serious incident that is still open, an imminent service failure or a security threat that cannot wait.

Emergency does not mean *no rules*. It means a faster route with the same goal:

  • A clear reason why it cannot wait
  • A defined scope, so the change does not grow while people are under pressure
  • A rollback plan and a way to validate the result
  • Authorisation by someone independent of the person doing the work, if at all possible
  • A review afterwards, to learn whether it was truly an emergency and what to improve

Be strict about what qualifies. If "emergency" becomes the way to get a change through quickly, the type loses its meaning. Many organisations track the number of emergency changes and look at the trend.

How do the three types compare?

StandardNormalEmergency
RiskLow and well understoodLow to highUsually high, because of the pressure
ApprovalGiven in advance for the procedureBefore the change, depending on riskFast route, reviewed afterwards
PlanningRoutine, repeatablePlanned in advanceAs soon as possible
ExampleInstall approved softwareUpgrade the invoicing databasePatch a server under attack
Main controlThe agreed procedureAssessment and approvalJustification, scope and review

How do you decide which type to use?

Ask these questions in order:

  1. Is there an approved procedure for exactly this work? If yes, it is probably a standard change.
  2. Can it wait for a normal assessment? If yes, it is a normal change.
  3. Does waiting cause serious harm, such as an open serious incident or a security threat? If yes, it may be an emergency change.

When you hesitate between normal and emergency, ask who carries the risk if you wait. If the honest answer is "nobody, it is just inconvenient", it is a normal change with a short planning time.

How do you create good standard changes?

Standard changes are only as good as their procedure. A short routine helps:

  • Write the procedure down with the steps, the expected result and the backout.
  • Agree on the scope. For which services, teams or systems is it allowed?
  • Have it approved once by someone accountable.
  • Review it regularly. Retire procedures that are no longer used or no longer safe.
  • Keep an eye on failures. If a standard change causes incidents, it should go back to normal change status until it is fixed.

Are scheduling rules different for each type?

They should be consistent. Pre-approved does not mean exempt from schedule rules: if a period is blocked for changes, such as a freeze at the end of the year, a standard change is blocked too. For emergency changes, many organisations allow a recorded exception, with the reason and approval, because the alternative may be worse than the change.

How does this work in Bourgos?

When you create a change in Bourgos, you choose standard, normal or emergency, and the type decides how authorisation works.

  • Standard: you select an approved Standard Change Model from the Standard Change Catalog. A Change Manager or administrator maintains these models: a draft is approved before it can be used, and a retired model cannot be used for new work. The model prescribes the plans and can include ordered task templates. A standard change is pre-approved only after the model and schedule have been validated.
  • Normal: the change starts as pending and needs the configured number of eligible approval votes. A single rejection rejects the change.
  • Emergency: you provide a justification, a precise scope, rollback and validation plans, and a link to an open incident from the affected service. The change starts as pending and needs authorisation by an independent, delegated emergency manager. High-risk emergency changes also need a distinct service owner. Alternatively, a manager with a separate break-glass permission can record a two-hour, non-renewable exception, with a mandatory independent review afterwards. Requesters and implementers cannot approve their own work.

Scheduling applies to all types. Standard and normal changes cannot bypass a blocking blackout. An emergency authorisation can explicitly accept a blackout exception for its recorded scope, but not a required maintenance window.

Read how to create a standard, normal or emergency change, how to plan windows and approve a change and how to configure approvals, maintenance and availability policies. The overview is on our change management software page.

Frequently asked questions

Can a standard change become a normal change?

Yes. If a standard change turns out to be riskier than expected, or if the procedure no longer fits, treat it as a normal change and review the procedure.

Is an emergency change the same as a major incident?

No. A major incident is a serious service disruption. An emergency change is the controlled modification you may need in order to resolve it. A major incident can lead to an emergency change, but not every emergency change comes from a major incident.

Who authorises an emergency change?

Preferably someone who is independent of the person doing the work, with a clear delegation to do so. Agree on this in advance, so you do not have to find out at 2 a.m.

Do standard changes need a backout plan?

Yes. The backout is part of the procedure that is approved in advance.

How many emergency changes are acceptable?

There is no right number, but a rising trend is a warning sign. Look at why they were needed and what would have prevented them.