What is change management? A practical introduction
Learn what change management is, how risk assessment, approval and scheduling fit together and how to make changes safely without slowing everyone down.
Friday afternoon, 16:45. An engineer applies a "small" configuration update to the mail gateway. It has worked in the test environment, so what could go wrong? On Monday morning, half of the company cannot send email to external customers, and nobody remembers that anything was changed.
Plenty of incidents start this way. Change management exists to make changes on purpose, with eyes open, and with a way back if something goes wrong.
What is a change?
A change is the addition, modification or removal of anything that could have a direct or indirect effect on a service. That covers more than software releases: a firewall rule, a new version of an application, a database upgrade, a replacement network switch or a retired server are all changes.
A change is not an incident (something is broken) and not a service request (someone asks for something that is a normal part of your service). The difference is explained in incident vs service request vs problem vs change.
What is change management for?
In ITIL 4, the practice is called change enablement. The name says what it is for: enabling beneficial changes to go ahead, while keeping the risk under control. It is not meant to be a brake.
A good change process helps you to:
- Reduce incidents caused by changes, because risk is assessed beforehand
- Avoid conflicts, for example two teams changing the same system at the same time
- Know what changed, so you can find the cause when something breaks
- Get approval from the right people without asking everyone for everything
- Have a way back when a change does not work out
What does a change process look like?
The details differ per organisation, but most processes follow the same steps.
1. Describe the change
What will change, why, and which service is affected? A short, clear description helps everyone who needs to judge or carry out the change.
2. Assess the risk
Ask what could go wrong, how likely it is, and how bad the result would be. A change to a rarely used internal tool is not the same as a change to a payment system. A simple low, medium and high rating, with a few lines of explanation, is often enough.
3. Plan the work
Write down the implementation plan: the steps, who does what, and how you will check that it worked. Write down the backout plan too: how you return to the previous working situation if it does not. A change without a backout plan is a bet.
4. Choose a time
Pick a moment when the effect on users is smallest, and when the right people are available. Check for conflicts with other changes and with periods in which nothing may change, such as a month-end closing.
5. Get authorised
Somebody with the right authority decides whether the change may go ahead. ITIL 4 calls this role the change authority. It does not have to be one board or one person. It depends on the type of change, as the next section explains.
6. Carry it out and check the result
Do the work, record what happened and verify that the service really works afterwards. A change that was executed is not the same as a change that succeeded.
7. Close and learn
Close the change with a clear outcome. If it failed, or caused an incident, find out why, and adjust the process.
Do all changes need the same approval?
No, and that is the most important point in this article. If every change goes through the same heavy route, people either wait too long or find ways around the process. Most organisations distinguish three types:
- Standard changes are low-risk, well understood and repeatable. They are approved in advance, once, so each individual change can go ahead quickly.
- Normal changes need to be assessed and authorised before they are carried out.
- Emergency changes must happen urgently, for example to restore a service or to stop a security threat. They follow a faster route, with more review afterwards.
Read more in standard, normal and emergency changes.
What is a CAB?
A change advisory board (CAB) is a group that reviews changes. Many organisations still use one for high-risk changes. ITIL 4 does not require a CAB, and it points out that the change authority can be delegated to the people who know the most about the change. Reserve a meeting for the changes that benefit from discussion, and keep routine changes out of it.
How do changes relate to incidents and problems?
- A change can cause an incident. That is why you want to know what changed recently when something breaks.
- An incident can lead to an emergency change, when a fix cannot wait.
- A problem often ends in a change that removes the underlying cause. See from incidents to problems.
Link the records to each other, so that the story is easy to follow afterwards.
Common mistakes
- No backout plan. You only find out how to go back when you need it.
- Changes on Friday afternoon. Unless it is really the best moment, avoid it.
- One process for everything. Heavy for small changes, light for large ones.
- Approval as a formality. If approvers click without reading, the process only adds delay.
- Closing without checking. Verify that the service works before you close the change.
- Unrecorded changes. The change nobody wrote down is the one that is hardest to find.
How does this work in Bourgos?
In Bourgos, changes are created and managed by staff in ExpertHub. You choose a type (standard, normal or emergency), set the risk, add the implementation and backout plans, and choose a planned start and end. Bourgos validates the planned interval against the schedule rules that apply: blackout windows can block the change, and every applicable required maintenance window must allow the whole interval.
Approval and progress are separate things. Approval status says whether the implementation is authorised. The ticket status shows how far the change has progressed in your own lifecycle. A normal change starts as pending and needs the configured number of eligible approvals, and a single rejection rejects the whole change.
The work itself is divided into change tasks for different teams, which can run in a fixed order or in parallel. Closing tasks does not prove that a deployment worked, so the guides ask you to check the real outcome before closing the change. You can also link a change to the problem that it solves.
Start with the guides on creating a change, managing a change and its tasks, planning windows and approving a change and sequencing change tasks, or look at our change management software.
Frequently asked questions
What is the difference between change management and change enablement?
ITIL 4 uses the name change enablement for the practice. In daily use, the two terms mean the same thing: controlling changes so that beneficial changes can go ahead with an acceptable risk.
Do small organisations need change management?
Yes, in a lighter form. Even a short checklist (what changes, what could go wrong, how do we go back, who agrees?) prevents most avoidable incidents.
Do I need a CAB?
Not for every change. Use a board or a meeting for high-risk or complex changes, and let people with the right knowledge approve the rest.
What is a backout plan?
The steps you take to return to the previous working situation when a change fails. Write it before the change, not during the incident.
Who should approve a change?
The people who can judge the risk and who are accountable for the service. For many changes that is a service owner, for others a manager or a specialist.