Manage a change and its tasks
Authorized ExpertHub Change Management access. Editing, approval, work notes and CTASK actions have separate permissions.
A Change is a planned modification to an IT service or supporting infrastructure. Use it to coordinate risk assessment, scheduling, authorization and traceable execution, whether deploying an application version, updating a network rule or applying an emergency security fix.
Incident Management restores disrupted service; Problem Management investigates underlying causes. Either can motivate a Change, but neither replaces a controlled Change record. Each Change receives a unique reference such as CHG000123.
Before you start
Use ExpertHub → Changes for Change records and ExpertHub → Change Tasks for implementation tasks. Menu availability depends on enabled modules and your role. ServiceHub is not a general-purpose self-service Change-creation workflow.
Your organisation uses ITSM Lite for service-based working or CSM Full for configuration-connected working. CI fields and CI-specific maintenance restrictions depend on CSM Full, Configuration Management and the permitted interface.
Steps
- Open Changes and create a record or select an existing one. Review the intended outcome, Service and applicable Service Offering.
- Choose Standard, Normal or Emergency, assess risk, and document the implementation plan, backout plan and proposed dates. Emergency Changes require a justification.
- Resolve any applicable blackout or REQUIRED maintenance-policy conflicts before proceeding. An eligible Emergency exception can override a blackout, but cannot bypass REQUIRED maintenance restrictions.
- For a Normal Change, obtain the configured number of eligible approval votes. Check approval status separately from the tenant-configured ticket status.
- Organize execution with CTASKs, assigned teams and task order. Use parallel tasks only for work independent of ordered predecessors.
- Once approved, progress permitted Change and task statuses, and add worknotes with decisions, execution results and deviations.
- Verify the actual technical outcome and backout needs before moving the Change through its configured lifecycle to closure.
Expected result
The Change connects its purpose, service context, scheduling constraints, authorization and implementation tasks. Closing tasks alone does not establish that an external deployment or validation succeeded.
Approval and ticket status
Standard Changes are pre-approved only when created from an approved Standard Change Model and after schedule validation. Normal Changes start Pending and need the configured approval votes. Emergency Changes start Pending and require independent delegated authorization or a recorded, time-bounded break-glass execution exception.
Approval status answers whether implementation is authorized: Pending, Approved or Rejected. Ticket status describes progress through your organisation's lifecycle. A Pending or Rejected Normal Change may still receive permitted planning/documentation updates, but cannot advance its ticket status. Emergency progression follows its separate authorization or break-glass gate; a rejected, unexecuted Emergency may be closed without claiming implementation. After a terminal ticket status, only an administrator or Change Manager may change its status again; approval guards still apply.
Roles and responsibilities
- Administrators and Change Managers have broad Change editing rights and terminal-status authority. Change Managers can also delete CTASKs.
- Incident Managers can edit non-terminal Changes and add worknotes, but have no special terminal-status authority.
- Elevated users in the parent Change's assigned team can edit that Change and add worknotes, subject to approval and status guards.
- A Problem Manager can edit a Change they themselves linked or created from a Problem; the role does not grant unrestricted Change administration.
- CTASK permissions follow the task's own assigned team, which can differ from the parent Change team.
- Eligible approvers cast decisions on Pending Normal Changes. Membership of the implementation team does not by itself grant approval rights.
Related Problems and configuration
A Problem may require a Change to implement a permanent fix. Keep the Problem–Change link so reviewers can follow why the modification is needed. Creating a Change does not replace the Problem investigation or the Incident restoration workflow.
In CSM Full, related CIs establish technical scope and can add maintenance constraints. A Service Offering expresses delivery or support commitments; it is not a specific deployed Service Instance.
Worked example
A coordinator plans Customer Portal version 3.4 as a Normal Change, choosing the Service, PROD Offering and a valid release window. They record implementation, validation and backout plans. In this example the Service policy requires two approvals, so both eligible approvers must approve; either rejection vetoes the Change.
The team creates backup at order 1, deployment at order 2 and validation at order 3. Each sequential task waits for earlier tasks to be Closed or Cancelled. An independent communications task may run in parallel. After approval, teams execute the tasks and record results. An authorized person closes the Change only after verifying the real release outcome.
Important behaviour
Approval decisions, ticket-status edits, worknotes and task updates are separate actions with separate guards. Neither administrator rights nor an Emergency justification bypass REQUIRED maintenance policies. Pending Emergency execution requires the separate authorization or break-glass gate. Regular end users do not receive full Change Management access by default.
Standard Change Catalog and reusable task blueprints
Change Managers and administrators govern Standard Change Models through DRAFT → APPROVED → RETIRED. Approved models prescribe the implementation and backout plan and may constrain Service, Offering, assignment team and risk. They can include ordered sequential/parallel CTASK templates; creating a Standard Change generates those model-derived tasks automatically. Model-derived tasks cannot be deleted, although authorized users can adjust their execution order on the individual Change and add separate tasks.
Emergency governance and independent review
Emergency Changes need documented urgency, affected Service, incident or eligible external evidence, bounded scope, assignment, implementation, rollback and validation details. The initial approval is Pending. An independently delegated emergency manager must authorize LOW/MEDIUM risk; HIGH risk requires a second distinct delegated Service Owner decision. Explicit acceptance is needed for any blackout exception. Required maintenance schedules remain binding. Break glass permits only a two-hour, non-renewable scoped execution exception without retroactive approval. Complete or cancel CTASKs, record Successful/Failed/Rolled back outcome and obtain independent review within 24 calendar hours of authorization or activation; outstanding Action required blocks closure. Emergency oversight summarizes recent exceptions and overdue reviews.